|
Background
|
Coventry
City Council is in the process of implementing a city wide fibre
network, known as a Metropolitan
Area
Network
(MAN). This will bring great benefits to Coventry by providing
cost effective fast communications for public services across the
city.
This
project is the first of its kind in the UK and will make Coventry
more attractive to businesses looking to relocate to the region.
Coventry
Citywide BID is working with Coventry City Council in order to
utilise this new infrastructure together with additional fibre and
a wireless solution to deliver a CCTV & Broadband solution.
The BID element is approximately 25% of the overall Council
project.
|
|
Broadband
|
Although
it has always been recognised that not all businesses will want to
take up the broadband offer, those who do should ensure they have
registered their interest by completing the Broadband Agreement
which can be found on our website.
|
|
Crime Reduction /
CCTV
|
The
CCTV element of our crime reduction service will offer 24/7
actively monitored cameras across the 84 business areas within the
citywide BID area supported by mobile patrols and a Crime
Reduction Advisor.
Under
certain circumstances we have been able to provide a temporary
crime reduction solution over and above the mobile patrols.
|
|
CCTV &
Broadband Project Update
|
There
are a number of phases to this project summarised as
-
Preparation
- COMPLETE
-
Implementation
-
Central
Infrastructure
-
Physical
- COMPLETE
-
Broadband
- COMPLETE
-
CCTV
- COMPLETE
-
Rollout
Plan per Business Area - Commenced
-
Connectivity
to CCC infrastructure
-
Permissions
-
Installation
-
Project
Close
|
|
2b Rollout Plan
|
In
order to complete the rollout for each Business Area there are 3
dependencies. These 3 elements have to be in place
-
Connectivity
Each
site needs to be connected to Coventry City Council's
infrastructure and routed back to the Central Infrastructure. We
therefore have a dependency on the Council's project in order to
complete this element.
-
Permissions
Broadband Agreements need to be signed by landlords and tenants in order to
give us permission to erect the appropriate equipment.
-
Installation
Once
items I & II are in place Coventry City Council's contractor
will install and commission the appropriate equipment which will
provide the service.
|
|
NB
|
As
the BID rollout project is now well and truly under way, we are
looking at ways of accelerating the installation programme.
Where
we have completed connectivity to the CCC Infrastructure, we have
already found that Business Areas that are engaging with the BID
and giving the relevant permissions required have been able to
move up the schedule more quickly eg. Newgate Court is now live a
month earlier than the original project schedule.
|
|
|
Clicking
the link below will take you to a spreadsheet giving details of
the progress of specific business areas.
Here
you will see
-
Site
Name
Each
business area is allocated a number for additional clarity. If you
are unable to locate your business area, please call the BID and
we will advise which site number you come under.
-
Effort
This
is the number of man days required to complete a specific business
area. This will vary from site to site.
-
Start
Date
Although
we have started contacting all sites, this date refers to the
first day of preparation for site installation.
-
Target
End Date
This
date is the planned end date provided the dependencies are met.
-
Temporary
Crime Reduction Services
Where
we have identified opportunities to provide additional crime
reduction services.
-
Estimated
End Date
This
is the projected date change where dependencies have allowed us to
either complete sites ahead of schedule or have caused target end
date slippage.
-
Dependencies
-
Connectivity
-
Permissions
-
Installation
|
|